Speyside Way Resurfacing Work
Speyside Way Resurfacing Work
We were asked to resurface just over 1km of the Speyside way. It required some heavy landscaping to open up the track cutting to make it wide enough to ditch either side and install new culverts. Our Team added around 700m of new ditching making sure they landscaped in all excavation to look untouched. They then built up the height of the track by 200mm with a centre cambered surface to help disperse surface water. The team mananged to get this work completed in a very short time frame to mee the clients timescales.